Match the following: (1) Cost performance index (CPI) (a) % project completion project budget (2) Earned

Question:

Match the following:

(1) Cost performance index (CPI)

(a) % project completion × project budget

(2) Earned value

(b) BCWP - BCWS

(3) Schedule variance

(c) BCWP - ACWP

(4) Cost variance

(d) BCWP/BCWS

(5) Schedule performance index (SPI)

(e) BCWP/ACWP