Match the following: (1) Cost performance index (CPI) (a) % project completion project budget (2) Earned
Question:
Match the following:
(1) Cost performance index (CPI)
(a) % project completion × project budget
(2) Earned value
(b) BCWP - BCWS
(3) Schedule variance
(c) BCWP - ACWP
(4) Cost variance
(d) BCWP/BCWS
(5) Schedule performance index (SPI)
(e) BCWP/ACWP
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Construction Project Management Theory And Practices
ISBN: 9789332542013
2nd Edition
Authors: Kumar Neeraj Jha
Question Posted: