What is the primary objective the customer's project manager focuses on when selecting a contract type? A.

Question:

What is the primary objective the customer's project manager focuses on when selecting a contract type?
A. Transferring all risk to the contractor
B. Creating reasonable contractor risk with provisions for efficient and economical performance incentives for the contractor
C. Retaining all project risk, thus reducing project contract costs
D. None of the above