5 The performance of a project was evaluated 10 weeks after its start. Table 15 gives the...

Question:

5 The performance of a project was evaluated 10 weeks after its start. Table 15 gives the relevant information.

a. On the same Gantt chart, show the project plan and the project progress, and discuss the two.

b. Calculate the SI for each organizational unit U1 and U2 and for the project as a whole.

Discuss.

TABLE 15 Immediate Normal Organization Percent Money Activity predecessors time Budget unit complete spent A – 4 $90 U1 100 $110 B A 2 $35 U2 100 $20 C A 6 $75 U2 40 $40 D B 3 $60 U1 80 $90 E C 10 $80 U1 0 0 F – 2 $40 U2 100 $40 G F 5 $55 U1 50 $30 H F 7 $80 U2 100 $60 I D, E, G 1 $40 U2 0 0 J H 10 $100 U1 0 0

c. Repeat part

(b) for the CI.

d. On the basis of past performance, update the expected completion time and budget.
State your assumptions.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Question Posted: