The following data concern an activity that has to be performed as part of a project: a.

Question:

The following data concern an activity that has to be performed as part of a project:

Expected duration (days) Standard deviation of the duration Expected labor-days Standard deviation of

a. What is the probability that completing the activity on time will require at least a 10% addition to the expected labor-days? 

b. A crew of three workers is assigned to this activity. What is the probability that it will be completed in fewer than 11 days? 

State your assumptions for both parts.  