The precedence relations and crew size required to complete a project are given in Table 5. For

Question:

The precedence relations and crew size required to complete a project are given in Table 5. For example, activity E, which comes after activity C, requires 10 weeks for its completion by a crew of six people. 

TABLE 5 Activity A B C D E F G H I J Immediate predecessors A A B C D F D, E, G H Time (weeks) 4 2 6 3 10 2 5

a. Construct an early-start Gantt chart and identify the critical path. 

b. Calculate and chart the labor profile required to complete the project for both an early-start and a late-start schedule. 

c. Level the required labor as much as possible with the goal of completing the project within the time period specified in part (a).

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Project Management Processes Methodologies And Economics

ISBN: 9780130413314

2nd Edition

Authors: Avraham Shtub, Jonathan F. Bard, Shlomo Globerson

Question Posted: