Omega 2 Project. Using the complexity weighting scheme shown in Table 5.2 and the following function point
Question:
Omega 2 Project. Using the “complexity weighting” scheme shown in Table 5.2 and the following function point complexity weight table, estimate the total function point count. Assume historical data suggest five function points equal one person a month and six people have been assigned to work on the project.
a. What is the estimated project duration?
b. If 20 people are available for the project, what is the estimated project duration?
c. If the project must be completed in six months, how many people will be needed for the project?