Assume you are the project manager for the Tidal 2 software project. You have been asked to

Question:

Assume you are the project manager for the Tidal 2 software project. You have been asked to calculate the expected cost for the project. Your company’s database indicates hat developers can handle eight function points each person-month and that the cost per developer at your firm is $5,000 per month. You and your team of five developers have come up with the following requirements:

Using the “complexity weighting” scheme shown in Table 5.2 and the information provided, calculate the total number of function points, the estimated cost, and the estimated duration of the Tidal 2 project.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Project Management The Managerial Process

ISBN: 9781260570434

8th Edition

Authors: Eric W Larson, Clifford F. Gray

Question Posted: