You are a project manager for Star Light Strings. Star Light manufactures strings of lights for outdoor
Question:
You are a project manager for Star Light Strings. Star Light manufactures strings of lights for outdoor display. Their products range from simple light strings to elaborate lights with animal designs, bug designs, memorabilia, and so on. Your newest project requires a scope change.
You have documented the characteristics of the product and its functionality using which of the following tools and techniques?
A. Change control system B. Corrective action C. Configuration management D. Updates to the scope management plan