Your project has experienced some changes to the agreed-upon WBS elements. The changes were approved through the
Question:
Your project has experienced some changes to the agreed-upon WBS elements.
The changes were approved through the proper change control process. The WBS changes may in turn require which of the following?
A. Scope changes B. Cost changes C. Schedule revisions D. Risk response changes