For a particular work package, the budgeted cost as of April 30 is $18,000. Suppose, as of
Question:
For a particular work package, the budgeted cost as of April 30 is $18,000. Suppose, as of April 30, the supervisor determines that only 80 percent of the scheduled work has been completed and the actual expense is $19,000. What is the BCWP? Compute AV, SV, CV, SPI, and CPI for the work package.