Using the status chart in Figure 11-20: a. Estimate AV, SV, CV, and TV, and compute SPI
Question:
Using the status chart in Figure 11-20:
a. Estimate AV, SV, CV, and TV, and compute SPI and CPI for Week 30.
Interpret the results.
b. Compute ETC and EAC. Estimate the revised completion date and sketch the lines for forecast ACWP and forecast BCWP.
Step by Step Answer:
Related Book For
Project Management For Business Engineering Principles And Practice
ISBN: 286248
2nd Edition
Authors: John M. Nicholas
Question Posted: