Question:
I would like to use Earned Value Analysis to track progress on internal projects, but we work in a weak matrix environment where salaries are confidential. What should I do?
A. Figure salary costs only for workers who are willing to disclose their salary to you.
B. Get confidential organizational salary data after a promise to do your rE~ports only at home.
C. Estimate salaries for workers on your projects and use the estimates in your earned value analysis.
D. Salary amounts that are not 100 percent accurate are worthless, so do not bother.