Reconfigure the network in Figure 11.21 using the critical chain approach. Remember to reconfigure the activities to
Question:
Reconfigure the network in Figure 11.21 using the critical chain approach. Remember to reconfigure the activities to late start where appropriate. What is the original critical path? What is the original project duration? How much feeder buffer should be applied to the noncritical paths? What is the length of the project buffer? Assume the 50% likelihood is exactly half the duration of current project activities.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Project Management Achieving Competitive Advantage
ISBN: 978-0133798074
4th edition
Authors: Jeffrey K. Pinto
Question Posted: