Using the following information, develop an activity network for Project Alpha. Activity Preceding Activities A .. ---
Question:
Activity Preceding Activities
A ………………………….. ---
B ………………………….. A
C ………………………….. A
D ………………………….. B, C
E ………………………….. B
F ………………………….. D
G ………………………….. C
H ………………………….. E, F, G