What is the time estimate of an activity in which the optimistic estimate is 2 days, pessimistic

Question:

What is the time estimate of an activity in which the optimistic estimate is 2 days, pessimistic is 12 days, and most likely is 4 days? Show your work.
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: