Why must lag times be scheduled between tasks in a project network diagram? A. Lag times allow
Question:
Why must lag times be scheduled between tasks in a project network diagram?
A. Lag times allow the team to take a break.
B. Lag times reflect instances when task overruns are anticipated.
C. Lag times reflect weekends and holidays.
D. Lag times allow other events to be completed before successor tasks can begin.