Why must lag times be scheduled between tasks in a project network diagram? A. Lag times allow

Question:

Why must lag times be scheduled between tasks in a project network diagram?

A. Lag times allow the team to take a break.

B. Lag times reflect instances when task overruns are anticipated.

C. Lag times reflect weekends and holidays.

D. Lag times allow other events to be completed before successor tasks can begin.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

It Project Management

ISBN: 9780071700436

3rd Edition

Authors: Joseph Phillips

Question Posted: