You are considering the decision of whether or not to crash your project. After asking your operations

Question:

You are considering the decision of whether or not to crash your project. After asking your operations manager to conduct an analysis, you have determined the “precrash” and “postcrash” activity durations and costs, shown in the following table (assume all activities are on the critical path):

image text in transcribed
a. Calculate the per day costs for crashing each activity
b. Which are the most attractive candidates for crashing? Why?
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: