As the following indicates, there is a lot involved in cooking a meal. A man has to
Question:
As the following indicates, there is a lot involved in cooking a meal. A man has to cook a meal for his friends. The meal has to be ready at 7 p.m. The shopping still has to be done. There are three courses: soup, main course, dessert. The main course consists of potatoes, vegetables and steak.
A table of activities (Table 4.12) is shown hereafter.
a Make a network diagram based on this table of activities. Which of the activities are on the critical path?
b What is the duration of this ‘project’?
c Make a Gantt chart based on the network diagram.
d Because the potato peeler cannot be found, a new one has to be bought.
This means that activity D lasts 90 minutes instead of 7 minutes. What will the duration be now? Use the network diagram.