Question: Project planning deals with the following activities EXCEPT ____ A. developing the scope statement B. identifying deliverables and creating the work breakdown structure C. *
Project planning deals with the following activities EXCEPT ____ A. developing the scope statement B. identifying deliverables and creating the work breakdown structure C. * finalize all activities across all of the process groups to formally close the project or a project phase D. estimating the resource requirements for the activities