A project is in its 50th week and has an actual cost of $300,000 for the work performed to date. The budgeted cost of that

A project is in its 50th week and has an actual cost of $300,000 for the work performed to date. The budgeted cost of that work is $400,000. It expected to have completed $500,000 worth of work by this time. The budget for the entire project is $1,000,000. What is the:

a. CV

b. SV

c. CPI

d. EAC (provide two possible values. Show the formulas you use in calculating each)

Step by Step Solution

3.42 Rating (152 Votes )

There are 3 Steps involved in it

Step: 1

AC actual cost 300000 PV planned value 400000 EV earned value 500000 BAC 1000000 a ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management in Practice

Authors: Samuel J. Mantel Jr., Jack R. Meredith, Sco

4th edition

470533013, 978-0470533017

More Books

Students also viewed these Accounting questions