Question

1 Approved Answer

Supplier ships components in lots of size 5000. A single-sampling plan with n=50 and c=2 is being used for receiving inspection. Rejected lots are screened,

Supplier ships components in lots of size 5000. A single-sampling plan with n=50 and c=2 is being used for receiving inspection. Rejected lots are screened, and all defective items are reworked and returned to the lot.

a. Draw the OC curve for this plan.

b. Find the level of lot quality that will be rejected 90% of the time.

c. Management has objected to the use of the above sampling procedure and wants to use a plan with an acceptance number c=0, arguing that this is more consistent with their zero-defects program. What do you think of this?

d. Design a single-sampling plan with c=0 that will give a 0.90 probability of rejection of lots having the quality level found in part (b). Note that the two plans are matched at the LTPD point. Draw the OC curve for this plan and compare it to the one for n=50 and c=2 in part (a).

Step by Step Solution

3.49 Rating (166 Votes )

There are 3 Steps involved in it

Step: 1

a Draw the OC curve for this plan Answer I draw the OC curve using excel b Find the level of lot quality that will be rejected 90 of the time Answer Since n5020 and p505000 01 the number of nonconform... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Introduction To Statistical Quality Control

Authors: Douglas C Montgomery

7th Edition

1118146816, 978-1-118-3225, 978-1118146811

More Books

Students also viewed these Economics questions