Question
The project is to produce 200 widgets and is scheduled to take five weeks. Each unit is planned to cost $90. The project is severely
The project is to produce 200 widgets and is scheduled to take five weeks. Each unit is planned to cost $90. The project is severely cost constrained. Performance data for the project at the end of week three is presented below:
• 120 total units were planned to be produced
• 130 units have actually been produced
• The financial manager reported that the business had actually spent $13,000 on the project by the end of week three.
a. Quantify cost variance. Is the project ahead or behind budget?
b. Quantify schedule variance. Is the project ahead or behind schedule?
c. Quantify cost performance efficiency. Is the project performing better or worse than planned?
d. Quantify schedule performance efficiency. Is the project performing better or worse than planned?
e. What is the forecast of project cost at completion (Estimate At Completion EAC) assuming current cost performance efficiency remains the same? How much budget variance is expected at completion?
f. What is the forecast of funding needed to complete the project (from this point forward Estimate To Complete ETC)?
g. What cost performance efficiency would be required for the remainder of the project to complete the project within the original budget?
h. As the project financial manager, what recommendations would you make?
Step by Step Solution
3.40 Rating (156 Votes )
There are 3 Steps involved in it
Step: 1
a Quantify cost variance Is the project ahead or behind budget Ans Cost variance CV Earned Value Act...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Document Format ( 2 attachments)
607ec5e7716ba_6721.pdf
180 KBs PDF File
607ec5e7716ba_6721.docx
120 KBs Word File
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started