1 1 - 2 4 Using PERT, Ed Rose was able to determine that the expected project completion time for the construction of a pleasure

11-24 Using PERT, Ed Rose was able to determine that the expected project completion time for the construction of a pleasure yacht is 21 months and the project variance is 4.
a. What is the probability that the project will be completed in 17 months or less?
b. What is the probability that the project will be completed in 20 months or less?
c. What is the probability that the project will be completed in 23 months or less?
d. What is the probability that the project will be completed in 25 months or less?
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Successful Project Management

Authors: Jack Gido, Jim Clements

4th Edition

9780324656152, 324656130, 978-0324656138

More Books

Students also viewed these General Management questions