1. (14 Points) An assembly line is to be designed to operate eight hours per day to supply a demand of 360 units per day.

image text in transcribed
1. (14 Points) An assembly line is to be designed to operate eight hours per day to supply a demand of 360 units per day. Given the tasks with times and precedence relationships as shown bilow a. Draw the precedence diagram for the tasks (4 pts.). b. Assign tasks to workstations using the following decision rules: b. Assign the eligible task with the most tasks directly dependent on it. c. If there is a tie, assign the eligible task with the longest task time. Show your complete step by step work. (7 pts.) c. Determine the efficiency delay of the assembly line ( 3pt.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managing Supply Chain and Operations An Integrative Approach

Authors: Thomas Foster, Scott E. Sampson, Cynthia Wallin, Scott W Webb

1st edition

132832402, 978-0132832403

More Books

Students also viewed these General Management questions

Question

Add or subtract as indicated. 4x + 1 x + 5 1 2 X + 10 x2+5r

Answered: 1 week ago