1. ( 30 points) We have a project consisting of the activities provided in the following table. The table shows the activity names, activity relations,
1. ( 30 points) We have a project consisting of the activities provided in the following table. The table shows the activity names, activity relations, and activity durations. To determine the project schedule, draw the activity relation network following the activity on node (AON) convention. Also, compute earliest start-finish time, latest start-finish time, and slack time for each activity. Finally, determine the critical path and project completion time