1. A Project has been defined to contain the following list of activities along with their required times for completion and predecessor(s) Activity Immediate activity
1. A Project has been defined to contain the following list of activities along with their required times for completion and predecessor(s)
Activity | Immediate activity | Time (weeks) | Predecessors |
---|---|---|---|
1 | Collect requirements | 3 | |
2 | Analyze processes | 2 | 1 |
3 | Analyze data | 2 | 2 |
4 | design processes | 6 | 2 |
5 | design data | 3 | 3 |
6 | design screens | 2 | 3,4 |
7 | design reports | 4 | 4,5 |
8 | program | 5 | 6,7 |
9 | test and document | 7 | 7 |
10 | install | 2 | 8,9 |
a) Draw a network diagram
b) Calculate the earliest expected completion time
c) Show the critical path in your network diagram
d) What would happen if activity 6 were revised to take six weeks instead of two weeks?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started