1. Below is a network diagram that represents a university revamp project.The project manager analyzes this project using the critical path (CP) method. Activity durations

1. Below is a network diagram that represents a university revamp project.The project manager analyzes this project using the critical path (CP) method. Activity durations are indicated on the network.

(a) Which is the CP?

(b) Calculate the duration of the CP.

(c) Calculate the amount of slack time at activity H.

(d) If activity I were delayed by ten time-units, what would be the impact on the project duration?

image text in transcribed
\f

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Systems Approach to Planning Scheduling and Controlling

Authors: Harold Kerzner

10th Edition

978-047027870, 978-0-470-5038, 470278706, 978-0470278703

More Books

Students also viewed these General Management questions

Question

=+1. Choose an appropriate template for a schematic report

Answered: 1 week ago