Answered step by step
Verified Expert Solution
Question
1 Approved Answer
1. Below is a network diagram that represents a university revamp project.The project manager analyzes this project using the critical path (CP) method. Activity durations
1. Below is a network diagram that represents a university revamp project.The project manager analyzes this project using the critical path (CP) method. Activity durations are indicated on the network.
(a) Which is the CP?
(b) Calculate the duration of the CP.
(c) Calculate the amount of slack time at activity H.
(d) If activity I were delayed by ten time-units, what would be the impact on the project duration?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started