Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

1) Calculating Contingency Reserves Using Expected Value Method - Guidance Note Step 1 List each contingency that could increase your expenses. For example, suppose that

image text in transcribed

image text in transcribedimage text in transcribed

1) Calculating Contingency Reserves Using Expected Value Method - Guidance Note Step 1 List each contingency that could increase your expenses. For example, suppose that these contingencies include having to i) add extra personnel to the project, ii) outsourcing to outside contractors, ii) failing to meet your soft deadline iv) experiencing equipment malfunction. Step 2 Estimate each of these contingency's costs. (If they were to occur). For example, suppose that the four contingencies would cost you, respectively, i) $32,000, ii) $48,000, iii) $20,000 and iv) $12,000. Step 3 Estimate the probabilities of each of the contingencies actually occurring. For example, suppose that the contingencies have, respectively, a 1) 5 percent, ii) 5 percent, iii) 10 percent and iv) 2 percent chance of occurring. Step 4 Multiply each contingency's cost by its probability. Continuing the example, i) 5 percent of $32,000 is $1,600, ii) 5 percent of $48,000 is $2,400, iii) 10 percent of $20,000 is $2,000 and iv) 2 percent of $12,000 is $240. Step 5 Add these values together. The sum of the values in this example is $6,240. You would need $6,240 in contingency reserves. EXERCISE 1) Calculate contingency reserves using expected value method. PROJECT DATA Project One %Probability Cost of of Contingencies Contingency List of contingencies Reserve Extra personnel to project 23570 0.04 Outsourcing to outside contractors 16900 0.06 Failing to meet deadline 46000 0.08 Equipment breakdown 2300 0.03 TOTAL RESERVE Project Two %Probability Cost of of Contingencies Contingency List of contingencies Reserve extra personnel to project 64780 0.06 outsourcing to outside contractors 42000 0.05 Failing to meet deadline 19700 0.09 equipment breakdown 4200 0.02 TOTAL RESERVE Project Three %Probability Cost of of Contingencies Contingency List of contingencies Reserve extra personnel to project 35600 0.07 outsourcing to outside contractors 22000 0.07 Failing to meet deadline 52000 0.12 equipment breakdown 6700 0.03 TOTAL RESERVE Project Four %Probability Cost of of Contingencies Contingency List of contingencies Reserve extra personnel to project 34600 0.03 outsourcing to outside contractors 19300 0.03 Failing to meet deadline 24700 0.08 equipment breakdown 4500 0.02 TOTAL RESERVE 1) Calculating Contingency Reserves Using Expected Value Method - Guidance Note Step 1 List each contingency that could increase your expenses. For example, suppose that these contingencies include having to i) add extra personnel to the project, ii) outsourcing to outside contractors, ii) failing to meet your soft deadline iv) experiencing equipment malfunction. Step 2 Estimate each of these contingency's costs. (If they were to occur). For example, suppose that the four contingencies would cost you, respectively, i) $32,000, ii) $48,000, iii) $20,000 and iv) $12,000. Step 3 Estimate the probabilities of each of the contingencies actually occurring. For example, suppose that the contingencies have, respectively, a 1) 5 percent, ii) 5 percent, iii) 10 percent and iv) 2 percent chance of occurring. Step 4 Multiply each contingency's cost by its probability. Continuing the example, i) 5 percent of $32,000 is $1,600, ii) 5 percent of $48,000 is $2,400, iii) 10 percent of $20,000 is $2,000 and iv) 2 percent of $12,000 is $240. Step 5 Add these values together. The sum of the values in this example is $6,240. You would need $6,240 in contingency reserves. EXERCISE 1) Calculate contingency reserves using expected value method. PROJECT DATA Project One %Probability Cost of of Contingencies Contingency List of contingencies Reserve Extra personnel to project 23570 0.04 Outsourcing to outside contractors 16900 0.06 Failing to meet deadline 46000 0.08 Equipment breakdown 2300 0.03 TOTAL RESERVE Project Two %Probability Cost of of Contingencies Contingency List of contingencies Reserve extra personnel to project 64780 0.06 outsourcing to outside contractors 42000 0.05 Failing to meet deadline 19700 0.09 equipment breakdown 4200 0.02 TOTAL RESERVE Project Three %Probability Cost of of Contingencies Contingency List of contingencies Reserve extra personnel to project 35600 0.07 outsourcing to outside contractors 22000 0.07 Failing to meet deadline 52000 0.12 equipment breakdown 6700 0.03 TOTAL RESERVE Project Four %Probability Cost of of Contingencies Contingency List of contingencies Reserve extra personnel to project 34600 0.03 outsourcing to outside contractors 19300 0.03 Failing to meet deadline 24700 0.08 equipment breakdown 4500 0.02 TOTAL RESERVE

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Raising Venture Capital

Authors: Rupert Pearce, Simon Barnes

1st Edition

0470027576, 978-0470027578

More Books

Students also viewed these Finance questions

Question

What are the objectives of job evaluation ?

Answered: 1 week ago

Question

Write a note on job design.

Answered: 1 week ago

Question

Compute the derivative of f(x)cos(-4/5x)

Answered: 1 week ago

Question

Discuss the process involved in selection.

Answered: 1 week ago