Question

1 Approved Answer

1- Complete the time study by filling in the circles. Then, calculate a standard time. Assume a 10% allowance on job time. Time Check Finishing

1- Complete the time study by filling in the circles. Then, calculate a standard time. Assume a 10% allowance on job time. Time Check Finishing Time Starting Time Elapsed Time TEBS TEAF Total Check Time 0.45 Effective Time Ineffective Time 0.00 Total Recorded Time Unaccounted Time Recording Error % 8:11 0.00 0.00 Time Study Observation Form Element No. and Description Note Cycle 1 2 A RW OT 110 55 130 83 NT Standard time Study No.: Operation: B RW OT NT 110 75 130 00
image text in transcribed
1- Complete the time study by filling in the circles. Then, calculate a standard time. Assume a 10% allowance on job time. Standard time

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Today

Authors: Terri A. Scandura, Kim Gower

1st Edition

1506385877, 978-1506385877

More Books

Students also viewed these General Management questions