Question
1 Approved Answer
1. Define the objectives, scope and assumptions for this project 2. Draw a Gantt chart by hand (or can use Excel, whatever is quicker). What
1. Define the objectives, scope and assumptions for this project
2. Draw a Gantt chart by hand (or can use Excel, whatever is quicker). What is the projected completion date before any time reduction is done? (In class, we'll do this step in MS Project as a tutorial)
3. Should George attempt to reduce the project completion time? If so, how?
Case:
List of Activities Estimates Activity Description Immediate Predecessor Time (weeks) A Obtain funding approval 1 B Finalize product design A 1 Build and deliver new equipment (Equip Inc.) A 8 Build dies/tools B 12 E Install equipment 1 F Train workers D,E 1 G De-bug process F 1 H Establish advertising plan A 1 I Finalize package and artwork H 2 J Advertise H 12 K Raw material delivery (RawMat Inc.) D,I 2 L Initial production run G, K 3 M Ship product J, L 1
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started