Question
1 Approved Answer
1) Given this cumulative data, taken from the Integrated Program Management Report, what is the estimate at completion (EAC), using the cost performance index (CPI)
1) Given this cumulative data, taken from the Integrated Program Management Report, what is the estimate at completion (EAC), using the cost performance index (CPI) as the performance factor for the Cooling System Work Breakdown Structure (WBS) element? (Note: use 3 decimal places on all interim calculations)
(IMAGE DESCRIPTION: WBS number 1.1.3.10, Cooling System, has a BCWS of 1830, a BCWP of 1444, an ACWP of 1973, a BAC of 2291, and an EAC of 2706.)
A.) 3438.4
B.) 3045.4
C.) 3130.1
D.) 1157.1
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started