Question

1 Approved Answer

1 . MRP for Subassembly K Gross Requirements: Derived from the demand of P . Scheduled Receipts: 1 0 Ks at week 3 and 3

1. MRP for Subassembly K
Gross Requirements: Derived from the demand of P.
Scheduled Receipts: 10 Ks at week 3 and 30 Ks at week 6.
Projected On Hand: Calculated based on inventory, receipts, and requirements.
Net Requirements: Gross requirements minus projected on hand.
Planned Order Release: Net requirements adjusted for lead time.
2. MRP for Component G
Gross Requirements: 3 times the requirements for K.
On Hand Inventory: 40 Gs.
Net Requirements: Gross requirements minus on hand.
Planned Order Release: Based on net requirements and lead time of 1 week.
3. MRP for Component H
Gross Requirements: 4 times the requirements for K.
On Hand Inventory: 200 Hs.
Net Requirements: Gross requirements minus on hand.
Planned Order Release: Based on net requirements, lead time of 1 week, and minimum order size of 200 units.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management In The Supply Chain Decisions And Cases

Authors: Roger Schroeder, Susan Goldstein

8th Edition

1260368106, 9781260368109

More Books

Students also viewed these General Management questions

Question

3. 22.2c What is the house money effect? Why is it irrational?

Answered: 1 week ago

Question

Define Administration?

Answered: 1 week ago

Question

Exercises judgement in sharing sensitive information.

Answered: 1 week ago