Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

1. Use the following information to construct a Tracking Gantt chart using MS Project. Activities Duration Preceding Activities A 5 days none B 4 days

1. Use the following information to construct a Tracking Gantt chart using MS Project.

Activities Duration Preceding Activities

A 5 days none

B 4 days A

C 3 days A

D 6 days B, C

E 4 days B

F 2 days D, E

Highlight project status on day 14 using the tracking option and assuming that all tasks to date have been completed on time. Print/capture the output file.

2. Using the information in Problem 1, highlight the projects status on day 14 but assume that activity D has not yet begun. What would the new tracking Gantt chart show? Print/capture the output file.

  1. Use the following table to calculate project schedule variance based on the units listed. (Figures are in thousands.)

Schedule Variance Work Units

A

B

C

D

E

F

Total

Planned Value

20

15

10

25

20

20

110

Earned Value

10

10

10

20

25

25

Schedule variance

4. Using the data in the table below, complete the table by calculating the cumulative planned and cumulative actual monthly budgets through the end of June. Complete the earned value column on the right. Assume the project is planned for a 12-month duration and $250,000 budget.

Activity Jan Feb Mar Apr May Jun Plan % C Value

Staffing 8 7 15 100

Blueprinting 4 6 10 100

Prototype

Development 2 8 10 70

Full Design 3 8 10 21 67

Construction 2 30 32 25

Transfer 10 10 0

Monthly Plan

Cumulative

Monthly Actual 10 15 6 14 9 40

Cumul. Actual

5. Using the data from Problem 4, calculate the following values:

Schedule Variances

Planned Value (PV)

Earned Value (EV)

Schedule Performance Index (SPI)

Estimated Time to Completion

Cost Variances

Actual Cost of Work Performed (AC)

Earned Value (EV)

Cost Performance Index (CPI)

Estimated Cost to Completion

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Information Technology Project Management

Authors: Kathy Schwalbe

6th Edition

978-111122175, 1133172393, 9780324786927, 1111221758, 9781133172390, 324786921, 978-1133153726

More Books

Students also viewed these General Management questions

Question

Relate how unanticipated inflation can redistribute real income.

Answered: 1 week ago