1. You do not expect the types of variances that have occurred on the project to date to continue. If BAC = 800, ETC =

1. You do not expect the types of variances that have occurred on the project to date to continue. If BAC = 800, ETC = 275, PV = 300, ACC = 200, EV = 250, and CPIC = 1.25, what is the EAC?

A. 640

B. 750

C. 600

D. 550

2. You know that BAC = 375, PV = 300, AC = 200, and EVC = 250. Variances that have occurred on the project to date are not expected to continue. What is the ETC?

A. 75

B. 50

C. 125

D. 150

Please explain and do not copy from Chegg. otherwise i have to report the answer.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Horngrens Accounting, The Managerial Chapters

Authors: Tracie Miller Nobles, Brenda Mattison

13th Edition

0135982138, 9780135982136

More Books

Students also viewed these Accounting questions