1. You do not expect the types of variances that have occurred on the project to date to continue. If BAC = 800, ETC =
1. You do not expect the types of variances that have occurred on the project to date to continue. If BAC = 800, ETC = 275, PV = 300, ACC = 200, EV = 250, and CPIC = 1.25, what is the EAC?
A. 640
B. 750
C. 600
D. 550
2. You know that BAC = 375, PV = 300, AC = 200, and EVC = 250. Variances that have occurred on the project to date are not expected to continue. What is the ETC?
A. 75
B. 50
C. 125
D. 150
Please explain and do not copy from Chegg. otherwise i have to report the answer.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started