10 points Save Answer the project is currently slated to finish no later than Day 28. If that's the latest the project can finish, the
10 points Save Answer the project is currently slated to finish no later than Day 28. If that's the latest the project can finish, the latest the last activity in the network can finish is Day 28. Assuming that activity is 4 days long. What is the latest that the last activity can start? 20 24 24 28 1-4d i = 40 20 24 24 28 13 iz - 60 18 24 Day 25 Day 24 Day 28 Cannot determined from the information provided