15 Question 15 Based on the chart below, some of the identified risks do not occur and therefore activity B gets done in 3 weeks.

15 Question 15 Based on the chart below, some of the identified risks do not occur and therefore activity B gets done in 3 weeks. What is the effect on the project?

Select one: a. There will be three critical paths. b. The project will complete sooner if activity F starts immediately. c. The project is complete. d. Activity A will have more float.

image text in transcribed
PM Chart X Activity Preceding Estimate Activity (weeks) Start 0 C Start D C C E D B AE F E End B.F

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Business Statistics A Decision Making Approach

Authors: David F. Groebner, Patrick W. Shannon, Phillip C. Fry

9th Edition

013302184X, 978-0133021844

More Books

Students also viewed these General Management questions

Question

L A -r- P[N]

Answered: 1 week ago

Question

Do not go, wait until I come

Answered: 1 week ago

Question

Pay him, do not wait until I sign

Answered: 1 week ago