Answered step by step
Verified Expert Solution
Question
1 Approved Answer
15 Question 15 Based on the chart below, some of the identified risks do not occur and therefore activity B gets done in 3 weeks.
15 Question 15 Based on the chart below, some of the identified risks do not occur and therefore activity B gets done in 3 weeks. What is the effect on the project?
Select one: a. There will be three critical paths. b. The project will complete sooner if activity F starts immediately. c. The project is complete. d. Activity A will have more float.
PM Chart X Activity Preceding Estimate Activity (weeks) Start 0 C Start D C C E D B AE F E End B.FStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started