1Failure to take corrective actions in light of special cause variations will likely ______. A. have no damaging effects on the project; corrective actions are
1Failure to take corrective actions in light of special cause variations will likely ______.
A. have no damaging effects on the project; corrective actions are not needed for special cause variations
B. result in project efficiencies
C. result in future task delays and/or project failures
D. have a significant impact on the ability to finish the project on time