Question

1 Approved Answer

1.If an agency has an appropriation for construction for FY 2018 for $950,000,000 and the only order is for $900,000,000, and the order is on

1.If an agency has an appropriation for construction for FY 2018 for $950,000,000 and the only order is for $900,000,000, and the order is on October 15, 2018 for construction of a new building, would the order be allowable?T/F

2.Would an agency be able to pay an invoice on October 1, 2020 for an order processed on Sep 15, 2020 for a single-year fund (Budget Fiscal Year 2020)?Why or why not?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting and Finance An Introduction

Authors: Peter Atrill, Eddie McLaney

8th edition

129208829X, 1292088297, 978-1292088297

More Books

Students also viewed these Accounting questions

Question

fill in blank in middle and right. thank you

Answered: 1 week ago

Question

The quality of the argumentation

Answered: 1 week ago