Question

1 Approved Answer

2 0 2 2 2 0 2 3 Current year construction costs $ 3 , 3 0 0 , 0 0 0 $ 6 2

2022
2023
Current year construction costs
$ 3,300,000
$ 620,000
Estimated remaining costs to complete
600,000
-0-
Current year billings
3,100,000
1,400,000
Current year collections
3,000,000
1,500,000
Required
Calculate the following amounts for each method:
Completed Contract
Percentage of Completion
2022
2023
2022
2023
Gross Profit
$ ?
$ ?
$ ?
$ ?
Construction in progress year-end balance.
$ ?
$ ?
$ ?
$ ?
Costs in excess of billings (Billings in excess of costs)
$ ?
$ ?
$ ?
$ ?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting

Authors: Ray H. Garrison, Eric W. Noreen, Peter C. Brewer

13th Edition

978-0073379616, 73379611, 978-0697789938

More Books

Students also viewed these Accounting questions

Question

Write down the Limitation of Beer - Lamberts law?

Answered: 1 week ago

Question

Discuss the Hawthorne experiments in detail

Answered: 1 week ago

Question

Explain the characteristics of a good system of control

Answered: 1 week ago

Question

State the importance of control

Answered: 1 week ago