Question

1 Approved Answer

2. A project has been subdivided into five activities. Their immediate predecessors and the estimated activity durations (optimistic, most likely, and pessimistic) are shown in

2. A project has been subdivided into five activities. Their immediate predecessors and the estimated activity durations (optimistic, most likely, and pessimistic) are shown in Table 1

Table 1 Details of the network

Activity Immediate Predecessor Estimate duration (in days)

A - 1, 2, 3

B - 1, 3, 5

C A, B 3, 4, 5

D A, C 2, 2, 2

E C, D 1, 2, 21

(a) Draw the project network. Based on the mean activity durations, calculate all earliest and latest starting and finishing times, and the total floats of all activities. What is the critical path? What is its duration?

(b) Calculate the variance and standard deviation on the critical path.

(c) Calculate the probability that the project will be finished between 11 and 15 days.

(d) What is the probability that the project will be finished within 14 days? What is the probability that the project will be finished in exactly 14 days?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Modern Management Concepts And Skills

Authors: Samuel Certo, S Certo

15th global Edition

978-1292265193, 1292265191

More Books

Students also viewed these Accounting questions

Question

For the data of Exercise 12.2, estimate a2.

Answered: 1 week ago