2 . A student wants to develop a project using PERT to modify one of products which has poor sales. She has determined the following

2. A student wants to develop a project using PERT to modify one of products which has poor sales. She has determined the following activities, precedence relationships and time estimates in days for the project:
TIME estimate Exp Time Variance
Act to tm tp te Vt
a 4675.830.250
b 1232.000.111
c 5555.000.000
d 79129.170.694
e 2484.331.000
f 69108.670.444
a) Name all potential paths and corresponding durations
b) Calculate ES, EF, LS, LF, and slack for all activities.
c) How many days can activity "e" be delayed without extending project duration?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals of Management

Authors: Robbins, DeCenzo, Coulter

7th Edition

132996855, 0-13-610982-9 , 9780132996853, 978-0-13-61098, 978-0136109822

More Books

Students also viewed these General Management questions