2. C-U Engineering is evaluating a few potential projects and has $1 million to be allocated. Which of the projects should the company accept to
2. C-U Engineering is evaluating a few potential projects and has $1 million to be allocated. Which of the projects should the company accept to stay within the budget? How much does the budget constraint cost the company in terms of lost market value? The discount rate for each project is 11%. Project IRR (%) A B D E F G Investment ($ thousands) 300 200 250 100 100 350 400 NPV $ thousands 80 -8 45 15 10 70 45 17.2 10.7 16.6 12.1 11.8 18.0 13.5