2} E'u'M W1C 4 You are given the following data regarding the Earned Value results of a project. Assume that future cost estimates are accurate
2} E'u'M W1C 4 You are given the following data regarding the Earned Value results of a project. Assume that future cost estimates are accurate and do not change. There have been no change orders during this project. Calculate ETC; Em: and VAC. a. w Project B AC sazsooo ? BAC ETC