2 . If your earliest start is 8 and your latest start is 1 0 for the same activity in a CPM ( Critical Path

2. If your earliest start is 8 and your latest start is 10 for the same activity in a CPM (Critical Path Method) analysis, which of the following statement holds?
A. The earliest finish time must be 8 B. The slack for this activity is 2
C. The latest finish time must be 12 D. All of the above
E. None of the above
3. Flow time (not the theoretical flow time) can be defined as:
I. The time that a unit is being processed by the machines and workers in the system
II. The time that a unit which leaves the process has spent within the process
III. The time for a unit to move through the system

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management in Practice

Authors: Samuel J. Mantel Jr., Jack R. Meredith, Sco

4th edition

470533013, 978-0470533017

More Books

Students also viewed these General Management questions