2) Learning curve Raytheon is producing an air-to-air missile. The cost of the 500th missile is estimated to be $300,000 and the learning curve is
2) Learning curve
Raytheon is producing an air-to-air missile. The cost of the 500th missile is estimated to be $300,000 and the learning curve is 88%. What is the estimated cost of the 600th missile? What is the total cost of the lot of missiles from unit 601 to unit 700?