2.16. The opening backlog is 1100 units. Forecast demand is as shown here. Calculate the weekly production for level production if the backlog is to
2.16. The opening backlog is 1100 units. Forecast demand is as shown here. Calculate the weekly production for level production if the backlog is to be increased to 1200 units.
Problem 2.18
2.18. For the following data, calculate the number of workers required for level production and the resulting month-end inventories. Each worker can produce 9 units per day, and the desired ending inventory is 800 units. Why is it not possible to reach the exact ending inventory target?
\begin{tabular}{|c|c|c|c|c|c|c|c|c|} \hline \multicolumn{2}{|l|}{ Week } & 1 & 2 & 3 & 4 & 5 & 6 & Total \\ \hline \multicolumn{2}{|c|}{ Forecast Demand } & 1200 & 1100 & 1200 & 1200 & 1100 & 1000 & \\ \hline \multicolumn{2}{|c|}{ Planned Production } & & & & & & & \\ \hline \begin{tabular}{l} Projected \\ Backlog \end{tabular} & 1100 & & & & & & & \\ \hline \end{tabular} \begin{tabular}{|c|c|c|c|c|c|c|c|c|} \hline \multicolumn{2}{|l|}{ Month } & 1 & 2 & 3 & 4 & 5 & 6 & Total \\ \hline \multicolumn{2}{|c|}{ Working Days } & 20 & 24 & 12 & 22 & 20 & 19 & \\ \hline \multicolumn{2}{|c|}{ Forecast Demand } & 2800 & 3000 & 2700 & 3300 & 2900 & 3200 & \\ \hline \multicolumn{2}{|c|}{ Planned Production } & & & & & & & \\ \hline \begin{tabular}{l} Planned \\ Inventory \end{tabular} & 1000 & & & & & & & \\ \hline \end{tabular}
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started