23+ Given is the Total Time, Non-Value Added (NVA) Time and Essential Non-Value Added (ENVA) Time. Calculate the Process Cycle Efficiency NVA Time = 250
23+ Given is the Total Time, Non-Value Added (NVA) Time and Essential Non-Value Added (ENVA) Time. Calculate the Process Cycle Efficiency NVA Time = 250 seconds ENVA Time = 399 seconds Total Time = 999 seconds 4096 2596 C6596 V 3596