233 Test 2 ippians 4:1-19 n... he following table lists the components needed to assemble an end item. lead times, and quantities on hand B 1 12 End 3 0 C 4 7 D 4 27 E 2 13 Item LT (week Amount on hand F 3 30 OWI 2 4 Click here for the Excel Data Fe NO ..r 20 units of the end item are to be assembled, how many additional units of E are needed? (Hint You don't need to develop an MRP plan to determine this) b. In order for the end item is scheduled to be shipped at the start of week 16. What is the latest week that the order can be started and en be ready to chip on time? (Hint You don't need to develop an MRP plan for this part either) Item LT (week) Amount on hand End 3 0 B 1 12 C 4 7 D 4 27 E 2 13 F 3 30 G 2 4 H 3 0 Click here for the Excel Data Filo Endom 12 C Da H14 23 FO G a. I 20 units of the end item MRP plan to determine this) to be assembled, how many additional units of E are needed? (Hint You don't need to develop an b. An order for the end item is scheduled to be shipped at the stort or week 16. What is the latest week that the order can be started and still be ready to ship on time? Hint You don't need to develop an MRP plan for this part either Prev Next > MC 233 Test 2 ippians 4:1-19 n... he following table lists the components needed to assemble an end item. lead times, and quantities on hand B 1 12 End 3 0 C 4 7 D 4 27 E 2 13 Item LT (week Amount on hand F 3 30 OWI 2 4 Click here for the Excel Data Fe NO ..r 20 units of the end item are to be assembled, how many additional units of E are needed? (Hint You don't need to develop an MRP plan to determine this) b. In order for the end item is scheduled to be shipped at the start of week 16. What is the latest week that the order can be started and en be ready to chip on time? (Hint You don't need to develop an MRP plan for this part either) Item LT (week) Amount on hand End 3 0 B 1 12 C 4 7 D 4 27 E 2 13 F 3 30 G 2 4 H 3 0 Click here for the Excel Data Filo Endom 12 C Da H14 23 FO G a. I 20 units of the end item MRP plan to determine this) to be assembled, how many additional units of E are needed? (Hint You don't need to develop an b. An order for the end item is scheduled to be shipped at the stort or week 16. What is the latest week that the order can be started and still be ready to ship on time? Hint You don't need to develop an MRP plan for this part either Prev Next > MC