270 You are the project manager of the Nirvana project. The project's budget at completion is $600,000. You have spent $230,000 of your budget. You
270
You are the project manager of the Nirvana project. The project's budget at completion is $600,000. You have spent $230,000 of your budget. You are now 40% done with the project, but your plan called for you to be 45% complete with the work by this time. What is your cost variance? $30,000 O $270,000 0-$30,000 $240.000 Step by Step Solution