3. (1.7 pts. total) For the network shown in the figure below: B D F Finish 2 5 6 A Start 1 C E
3. (1.7 pts. total) For the network shown in the figure below: B D F Finish 2 5 6 A Start 1 C E 3 3 a) Calculate the Early and Late Start and Finish times of each of the activity. (1.2 pts.) b) Calculate and note the slack for each activity on the diagram. (0.3 pts.) c) What is the critical path of this project? (0.1 pts.) How long will the project take (project completion time)? (0.1 pts.)